For contractors delivering AI data centres, QPC recommends agreeing the available power, its conditions and supporting evidence before fixing equipment orders, specialist attendance or commissioning dates.
QPC attended the DCD Connect London keynote Powering the AI Economy – Can UK grid reform unlock data center growth? on 16 September 2026. [1] Its discussion of connection reform, readiness and flexible supply informs the tender and delivery checks below.
The reforms discussed concern Great Britain. The actions below are QPC recommendations that can inform projects elsewhere, subject to local requirements and the actual supply arrangements.
Build the programme around evidenced power availability
The keynote questioned how much acceleration individual projects could achieve and highlighted uncertainty around access to prioritisation. [2] Government subsequently confirmed that the Connections Accelerator Service can help identify opportunities, but does not guarantee an earlier connection date. [3]
QPC recommends keeping acceleration opportunities separate from the baseline until project-specific evidence supports them. Connect the outstanding network works, approvals, access and testing behind the power date to the contractor’s installation and commissioning activities.
If installation can finish before power arrives, test whether resequencing or changing specialist attendance would improve the forecast before authorising additional labour.
Contractor Actions and Key Considerations
- Link the network delivery programme to construction and commissioning; record missing information with a named owner and required decision date.
- Distinguish first energisation, capacity available for commissioning and capacity available for operation in the programme.
- Test a later-power scenario before committing acceleration costs, and agree when reduced float requires escalation.
Align procurement commitments with project readiness
Ofgem’s July 2026 consultation proposed a data centre commitment fee of £237,500–£712,500 per megawatt, alongside additional evidence of project progress. As checked on 5 October 2026, the consultation is closed and awaiting a decision. These are proposals, rather than an established charge for every project. [4]
The proposed milestones include evidence of a credible end-user, long-lead electrical equipment procurement, and financial and technical capability. [4] QPC’s recommendation is to assess how any confirmed requirements would affect funding authority and the timing of orders, without assuming the contractor must provide the connection security.
For future tenders, keep potential security and financing exposure separate from construction allowances. For live projects, distinguish reserving a manufacturing slot from authorising manufacture: each step should have an agreed design basis, approval and cancellation exposure.
Contractor Actions and Key Considerations
- Ask the employer to confirm applicable connection requirements and funding authority before non-cancellable procurement commitments.
- Record supplier deposits, cancellation liabilities and deferral options alongside design maturity and required delivery dates.
- Keep readiness evidence in controlled records, and assess proposed reforms as scenarios until their final requirements are confirmed.
Match phased power to commissioning and acceptance
The keynote discussed ramped and non-firm connection options as potential ways to use available network capacity. [5] Government’s consultation also identifies flexible alternatives for projects supported through the Connections Accelerator Service. [6] These options need assessment against the site’s actual commissioning and operating requirements.
QPC recommends asking the network provider to specify the capacity available at each stage, when it increases and what restrictions apply. The design and commissioning teams can then test whether the proposed supply supports each phase, including facility services and the agreed test sequence.
An earlier initial supply should trigger a review of sectional boundaries and acceptance criteria. Check whether shared systems or later works require outages or access through operating areas before treating a phase as independently deliverable.
Contractor Actions and Key Considerations
- Prepare a phase-by-phase demand schedule with the responsible technical teams, covering commissioning, facility services and operational loads.
- Obtain written confirmation of capacity, availability restrictions and the conditions for each increase in supply.
- Agree test methods, acceptance boundaries and any repeat attendance before committing the staged delivery programme.
Need support with your project?
We are currently helping contractors stay commercially protected while delivering complex projects.
Speak to us about how we can help you on your project.
Make power changes visible in the cost forecast
QPC recommends turning a changed power assumption into a coordinated project review. Use the same event reference across the programme, risk register, procurement schedule and forecast so that the team can see the combined consequence and decide what to do next.
Assess additional attendance, storage, preservation, repeat testing and remobilisation where relevant. Keep gross exposure separate from any assumed recovery, and avoid counting the same allowance twice. This gives management a clearer basis for comparing continued attendance, resequencing or deferral.
Contractor Actions and Key Considerations
- Update affected activities and commitments when the evidence behind a power date changes, rather than reporting physical progress alone.
- Assign an owner and decision date to each mitigation option, including the last useful point for deferring expenditure.
- Preserve the assumptions behind each forecast and check any contractual communications required by the actual agreement.
Three decisions for the next project review
Contractor Actions and Key Considerations
- Confirm the evidenced power sequence supporting the tender or live commissioning programme.
- Identify the next order or mobilisation decision that depends on funding, readiness or capacity confirmation.
- Agree the response to a later or restricted supply before the affected expenditure becomes unavoidable.
Disclaimer
Quantum Project Control is not a law firm and does not provide legal advice. This article is for general information purposes only and should not be relied upon as legal advice. For guidance on specific issues, please consult a qualified legal professional.
Article source notes
Retain these references with the public article. Event discussion is described generally without naming participants. Contractor actions and delivery implications are QPC recommendations.
[1] DCD official agenda, Opening Keynote: Powering the AI Economy – Can UK grid reform unlock data center growth?, 16 September 2026, 14:00–14:30, Energy Summit Stage.
Source [1] public reference
[2] Question-and-answer discussion on expected time to power and the Connections Accelerator Service. Records uncertainty discussed at the event; it does not establish an acceleration forecast.
[3] UK Parliament, written answer on Data Centres: Energy, answered 18 September 2026. States that Connections Accelerator Service support does not guarantee an earlier connection date.
Source [3] public reference
[4] Ofgem, Ofgem acts to free up grid capacity by tackling speculative data centre projects, 29 July 2026; and Proposed data centre connection reforms, consultation description and status. Fee range and proposed milestone categories verified; awaiting-decision status checked 5 October 2026.
Source [4] public reference
[5] Opening presentation’s discussion of flexible connection offers and subsequent answer on the Connections Accelerator Service. These were options discussed, not an assurance of site-specific suitability.
[6] UK Government, Accelerating electricity network connections for strategic demand, consultation, Policy Landscape — The UK’s Modern Industrial Strategy section. Identifies non-firm, ramped and profiled alternatives; checked 5 October 2026.
Source [6] public reference