For contractors assessing small modular reactor (SMR) power for data centres, the practical question is what evidence supports the project’s power date. QPC recommends treating the proposed nuclear supply as a workstream with its own funding, approval and delivery milestones before using it to fix construction commitments.
At DCD Connect London on 16 September 2026, QPC attended Plugging into the Atom – Can SMRs power Europe’s next generation of data centers? [1] The panel discussed financing, co-location and scaling. This article draws on attributed speaker observations; the contractor checks are QPC’s recommendations for current projects and future tenders.
Keep the commissioning plan and long-term energy strategy aligned
The panel discussed that near-term power arrangements and longer-term SMR development should be pursued together, rather than treated as competing choices. They compared lengthy UK grid connection and SMR development discussions. Those observations do not establish a standard lead time for either route. [2]
For QPC, the implication is to keep both planning horizons visible. A future nuclear proposal needs a clear relationship to the capacity supporting commissioning and early operation. The construction team should understand which route the employer is relying on, and when a change would affect the works.
Contractor Actions and Key Considerations
- Ask the employer and power provider to identify the supply supporting each commissioning phase, with dated evidence for capacity and availability.
- Record the SMR dependencies separately, including approvals, funding, procurement and first power; agree who provides updates and makes decisions.
- For a tender, state which power assumptions support the price and programme. For a live project, escalate changes before they affect installation or testing.
Make funding commitments visible before committing resources
The panel described a demand-led model in which electricity buyers, reactor vendors and government progressively develop an investable project. They distinguished early interest from later contractual commitments. They also emphasised the private partners needed to finance a first project, including the electricity buyer, sponsor, delivery contractor and bank. These were proposed approaches, not confirmation that any particular project had secured finance. [3]
QPC recommends turning that distinction into release gates for the construction programme. A power purchase agreement (PPA) concerns buying electricity; its existence alone should not be treated as evidence that all funding and delivery conditions are satisfied.
Contractor Actions and Key Considerations
- Request confirmation of the project’s actual commitment stage, outstanding funding conditions and authorised route to commencing each package.
- Agree what evidence releases design, equipment orders and mobilisation, and who can authorise expenditure while conditions remain open.
- Identify the cost and programme consequences of a delayed decision, including supplier reservations, remobilisation and changes to the power interface.
Check the site and power interfaces before fixing the design
It was stressed that reactor size, refuelling requirements, licensing and siting need to be considered for the specific technology and location. The panel also raised maintenance and resilience when discussing dedicated generation. Their discussion supports asking how the complete supply arrangement meets the operator’s requirements, rather than inferring resilience from generating capacity alone. [4]
A specific Great Britain distinction matters: the Office for Nuclear Regulation assesses reactor designs through Generic Design Assessment separately from applications for particular sites. Site licensing, relevant construction consent, environmental permits and planning permission are separate requirements before a new station can be built and operated. This is not a rule for every European jurisdiction and needs to be checked depending on the geographic location of your project. [5]
QPC recommends an agreed interface schedule connecting the energy development with the data centre design. Keep specialist nuclear responsibilities explicit alongside the contractor’s own works.
Contractor Actions and Key Considerations
- Ask the responsible specialists to map design assessment, site approvals and construction permissions, with their status, owner and affected milestones.
- Agree the boundaries for land, access, civil works, electrical connections, controls, testing and handover between the data centre and energy packages.
- Have the power provider and operator confirm how maintenance, refuelling and unavailable units are addressed in the supply and acceptance requirements.
Need support with your project?
We are currently helping contractors stay commercially protected while delivering complex projects.
Speak to us about how we can help you on your project.
Treat repeat projects as an opportunity with conditions
The panel discussed spreading risk across a fleet of projects; they supported learning from the first delivery before committing to wider repetition. These are development strategies, not proof that later projects will cost less or arrive sooner. [6]
For contractors, QPC recommends separating reusable design and procurement opportunities from unconfirmed future workload. Standardisation is worth testing where the vendor, site conditions, approvals and package boundaries support it.
Contractor Actions and Key Considerations
- Identify which designs and work packages could be repeated, and which require site-specific review before adoption.
- Keep proposed future phases separate from authorised scope; qualify volume assumptions used in pricing or supplier commitments.
- Capture first-project design changes, interface issues and delivery lessons before setting the baseline for the next phase.
Three decisions for the next project review
Contractor Actions and Key Considerations
- Agree the evidenced power basis for commissioning before committing the tender or updating the delivery baseline.
- Identify the next funding or approval decision that controls construction commitments, with an owner and decision date.
- Confirm the power interface and acceptance responsibilities before freezing affected designs or placing orders.
Disclaimer
Quantum Project Control is not a law firm and does not provide legal advice. This article is for general information purposes only and should not be relied upon as legal advice. For guidance on specific issues, please consult a qualified legal professional.
Article source notes
Publish these compact references with the article. Speaker observations are attributed views; actions and commercial implications are QPC recommendations.
[1] DCD, official session agenda, 16 September 2026, 15:30–16:15, Energy Summit Stage.
DCD session details and speaker list
[2] Panel response on near-term power and long-term nuclear development; comparison of grid connection and SMR development discussions.
[3] Panel explanation of progressive buyer, vendor and government commitments; discussion of partners and financing for a first project.
[4] Panel response on technology-specific siting, licensing and refuelling; preceding discussion of maintenance and resilience for dedicated generation.
[5] Office for Nuclear Regulation, Generic Design Assessment (GDA) of new nuclear power stations, opening explanation of design assessment and site-specific permissions. Great Britain; checked 5 October 2026.
ONR design assessment and site permission requirements
[6] Panel discussion of fleet-level risk and fallback arrangements; discussion of learning from the first project before wider deployment.
The agenda verifies identities and session details, not what was said. Transcript references identify the particular discussion; detailed evidence locators appear in the internal handoff.